Floor screed for an extension

An extension floor is screeded last, on top of the insulation: 65 mm of sand and cement, or 35 mm of liquid screed, and 25 mm over the pipes if there is underfloor heating. A 40 m² extension costs about €880–€1,360 in sand and cement or €960–€1,440 in liquid, with the screed supplied and laid.

The depth, the cost and the order of work, from the insulation up.

Free, no obligation. One local screeder prices it, not five.

  • €880–€1,36040 m² in sand and cement
  • €960–€1,44040 m² in liquid screed
  • 65 mmsand and cement on insulation
  • 80 daysdrying time at 65 mm
A worker in wellies spreading wet floor screed across a floor with a dappling bar

Where the screed comes in an extension

By the time the screeder arrives the extension is roofed, the windows are in and the first fix is done. Under the screed, from the ground up: hardcore, the radon barrier, the concrete slab, the insulation boards and a membrane over them. The screed is the last wet job in the room.

  1. The roof is on and the room is closed in. Rain on a fresh screed ruins the surface, and frost is worse.
  2. The insulation is down, tight and flat. Gaps between boards let screed run under and lift them.
  3. Pipes and ducts are in. Anything that crosses the floor goes under or through the insulation, not on top of it.
  4. The level is marked. The finished floor of the extension has to meet the old house at the door between them.

Price your screed

Four taps and the guide price is on screen. Your name and number come last, and only if you want a local screeder to price the floor properly.

Screed for an extension floor, about 40 m², in sand and cement: €880 to €1,360, supplied and laid.

Step 1 of 5

What is the screed for?

Tap the nearest one. The screeder checks the detail on the call.

How the price is worked out

It is the area multiplied by our guide rate: €22 to €34 a m² for sand and cement screed supplied and laid, and €24 to €36 a m² for liquid screed poured. One room under 25 m² is not priced by the m², because the pump, the crew and the delivery cost the same for a small floor as for a big one. Insulation, membranes, underfloor heating pipes and any digging out are separate lines. The screeder gives the firm price after seeing the drawings or the floor.

Meeting the floor of the old house

This is where extensions go wrong. The new floor is built up in layers and the old one is whatever it is. Work back from the finish: the tile or timber, its adhesive or underlay, then the screed. The top of the screed in the extension is set so the two finished floors line up at the opening.

If there is not enough height for 65 mm of sand and cement, liquid screed at 35 mm buys back 30 mm. A movement joint goes in the screed at the opening, where the new floor meets the old.

Sand and cement or liquid in an extension

Sand and cement

Depth on insulation
65 mm
40 m² supplied and laid
€880–€1,360
Drying before timber or vinyl
About 80 days
Suits
Any extension, and a utility or shower room that needs a slope

Liquid screed

Depth on insulation
35 mm
40 m² supplied and laid
€960–€1,440
Drying before timber or vinyl
About 35 days
Suits
Open-plan rooms, underfloor heating, tight floor heights

Asked before the pour

How much does it cost to screed an extension?

About €880–€1,360 for a 40 m² extension in sand and cement and €960–€1,440 in liquid screed. An extension under 25 m² is priced on the call.

How thick is the screed in an extension?

65 mm of sand and cement on insulation, or 35 mm of liquid screed. With underfloor heating, liquid screed needs 25 mm over the top of the pipes.

When is an extension screeded?

After the roof, windows and first fix, and before plastering if the plasterer agrees, or straight after. It has to be closed in and dry overhead.

Can the kitchen go in straight after the screed?

Units can go in after a week. The floor finish is what has to wait: about 80 days for timber or vinyl on 65 mm of sand and cement. Tiles can go down sooner with the right adhesive.

Everything on screed.ie

A worker in wellies spreading wet floor screed across a floor with a dappling bar

See the price before anyone rings

Tap the job, the area and the screed. If the figure suits, a single screeding contractor in your county rings you and prices the floor properly.